SPECIAL PROJECT

Globus Medical Steel Beam for Auditorium

Project Description

This project consisted of the removal of structural roof columns to create a new auditorium for training of medical professionals. The roof structure of the area being enlarged had to be completely shored up with structural scaffolding to carry the roof load during renovation. 

Project Location

Audubon, PA

 

Project Photos

Existing Warehouse structure before work proceeded.

New concrete reinforced foundations had to be installed.

Sawcutting of slab and new pier footers being installed.

New beams being delivered.

Connection plate on beam.

Each of these beam sections weighed over 3 tons.

30′ section of steel beam being erected.

30′ section of steel beam being erected.

Welding and detailing as required.

Area almost complete, ready to start removing temporary shoring.

Temporary shoring.

Cutting off and grinding down of existing columns which were removed.

Completion of erection of structural steel span ready for Auditorium construction to begin.

Completion of erection of structural steel span ready for Auditorium construction to begin.

Completion of erection of structural steel span ready for Auditorium construction to begin.

Completion of erection of structural steel span ready for Auditorium construction to begin.